Scholar99.com

Learning Simplified
Menu
  • Home
  • Project Management
  • About Us
  • Contact Us
  • Privacy Policy
  • Disclaimer

Home » Project Management » Fast Tracking And Crashing – Schedule Compression Techniques

Fast Tracking And Crashing – Schedule Compression Techniques

Ravi September 5, 2017
Share4
Share8
Tweet
Pin
12 Shares

Fast tracking and crashing are the schedule compression techniques in project management. These are powerful weapons for the project manager to deal primarily with project schedule and cost related concerns.

From the PMP exam perspective also, understanding the concepts of fast tracking and crashing are very important, as you can expect some questions on these concepts in the PMP exam.

First of all, what are schedule compression techniques and why do you need them?

In cases where your project activities, especially the activities on the critical path are getting delayed or has chances of getting delayed, generally project managers uses the schedule compression techniques to save your project schedule time and keep the project on track.

Fast Tracking and Crashing - Schedule Compression Techniques in Project Management

Table of Contents

  • Common Reasons To Apply Schedule Compression Techniques
  • Schedule Compression Techniques
  • Fast Tracking In Project Management
  • Fast Tracking Example
  • Crashing In Project Management
  • Crashing example
  • Conclusion

Common Reasons To Apply Schedule Compression Techniques

The following are some of the common reasons (but not limited to) for the project manager to apply the schedule compression techniques such as fast tracking or crashing.

  • Your project is getting delayed. And the project manager want to get the project back on track.
  • Project schedule has become un-realistic due to some reasons.
  • Due to some natural calamities, you miss the schedule.
  • Customer requests for early delivery because of some dependency which customer also did not expected earlier.
  • You see lot of uncertainties in the project, and to manage them you would need enough time in the project

Whatever be the reason, the schedule compression techniques comes to rescue the project manager from the schedule and cost related slippages in the project.

Schedule Compression Techniques

There are primarily two schedule compression techniques. They are

  1. Fast tracking
  2. Crashing

Fast Tracking In Project Management

As per the PMBOK guide, fast tracking is one of the schedule compression techniques in which activities or phases, which are normally planned to do in sequence, are performed in parallel for at least a portion of their duration.

Most of the time, the activities cannot be done in parallel completely due to the dependency that exists between the project activities. Otherwise, I do not see any reason, why those activities  are not initially planned in parallel.

For example, a software development project has two modules for which the coding is possible to do it in parallel to a certain extent, but not to its full extent because of the dependencies between the two modules.

Although fast tracking is very useful technique for the project manager, it comes with a price, if not used carefully.  Meaning that overusing fast tracking may result in lot of rework. Hence project manager should perform the necessary analysis before applying the fast tracking techniques on the project activities.

For this, project manager need to sit with the project team to understand, which activities are feasible to do it in parallel and to what extent? And also identify any potential risks to the projects such additional rework, quality issues, etc.…

Fast Tracking Example

For example see the project schedule in the below diagram, where total activities require 10 weeks of time, as they planned sequentially due to the dependencies.

Fast Tracking example

However by applying the fast tracking, activity 3 started early than planned in parallel to activit2, and completed the activity 3 after 1 week from activity 2 completion date.

One point to note is generally fast tracking if not overused, will not result any additional cost to the project and hence usually safe to use it, when feasible.

Remember that the key for fast tracking is always that some activities in the project are feasible to do it in parallel to a certain extent, if not completely.

But in some case you may not that type of activities in the project. Or even if you find, implementing fast tracking may result in more rework, which will cost more to the project. In those cases, better to avoid fast tracking and can see the feasibility of other schedule compression technique crashing.

Crashing In Project Management

Crashing is another schedule compression techniques, in which you add extra resources to the project activities, with no or minimum increase in the cost of the project.

So by adding extra resources to the activities which are at risk, the project manager would try to shorten the schedule of the activities.

So always extra resources come with their price. As a project manager you need to apply techniques to analyze whether this cost is manageable to the extent that the whole project is not at risk.

Crashing may not work in all circumstances. Sometimes adding extra resources may not help in compressing the schedule of the activities.

There is a famous saying, that project managers use sarcastically, 9 women cannot make a baby in one month.

Don’t mistake me. I just used this proverb to make everyone understand the context that, crashing may not be helpful in certain circumstances.

I see in lot of projects, some stakeholders always pressurize the project manager to shorten the schedule by using crashing in cases where it is not appropriate to use. As a project manager you would need to make the stakeholders clearly understand the feasibility and risks involved in applying the crashing in those special circumstances.

Also compare to fast tracking, crashing is expensive. Because additional resources add additional cost to the project.

Crashing example

Some example of crashing as we have already seen

  • adding extra resources to the activities,
  • asking resources to work for over time and pay them for their overtime,
  • Using the un-utilized resources because of the float or any dependency with other activity
  • Motivating the team to stretch for the extra mile and rewarding them in some or the other way.

Refer the below example where in the activities and schedule are represent the rows and columns respectively. And R1, R2, R3 and R4 are representing the resources.

Crashing example

Before applying the crashing 3 resources were there to complete the project within 10 weeks of schedule. Now by adding more resources in week7 and week8, the project shorten two weeks of schedule.

Conclusion

Now we have seen the what are schedule compression techniques and when to use them. We have seen two schedule compression techniques namely fast tracking and crashing.

Fast tracking is to run the activities in parallel, which was sequential according to the original plan. And crashing is about adding more resources to shorten the schedule. Both of the techniques has pros and cons. So the project manager should be conscious on how to use them carefully according to the situation at hand.

The major cons about fast tracking is that it may result in rework, and quality issues. On the other hand, the major cons for crashing is that it can be expensive, if not used properly.

Share4
Share8
Tweet
Pin
12 Shares
Share
Tweet
Pinterest
Linkedin
Reddit
Email
Prev Article
Next Article

Related Articles

Requirements Gathering Process - Collect-Requirements
Requirements Gathering is the process of exploring the requirements for …

Requirements Gathering | Collect Requirements Process and ITTO s

Critical Path Method
Critical path method (CPM) is the most important concept to …

Critical Path Method (CPM) – The Ultimate Guide To Critical Path Method

Network Diagram using precedence diagram method
Network diagram is primarily used to understand how the activities …

Network Diagram Using Precedence Diagramming Method OR Activity On Node

PMP Exam Day
PMP Exam day is an important day to remember in …

PMP Exam Day – Ultimate Guide to Dos and Don’ts on the The D-Day

2 Comments

  1. samir

    Thanks for specifying both technique simply

    October 11, 2018
    • Ravi

      Hi Samir,

      I am glad you liked it.

      Regards, Ravi

      October 13, 2018
  2. Anonymous

    Visitor Rating: 5 Stars

    October 22, 2019

Leave a Reply

Cancel reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.




Popular Posts

    Recent Posts

    • Construction-Assistant-Project-Manager-Salary-in-usa-and-india
      Construction Assistant Project Manager Salary in USA & India
    • What-is-a-Project-Scope-in-Project-Management
      What Is a Project Scope in Project Management?
    • What is Gold Plating
      What is Gold Plating in Project Management? Top 5 Causes …
    • What Is A Project In Project Management?
      What Is A Project in Project Management?
    • What-is-Pareto-Chart
      What is a Pareto Chart? | 80 20 Rule | …

    Find us on Facebook

    Get more stuff

    Subscribe to our mailing list and get interesting stuff and updates to your email inbox.

    Thank you for subscribing.

    Something went wrong.

    we respect your privacy and take protecting it seriously

    Scholar99.com

    Learning Simplified

    Important Links

    • About Us
    • Contact Us
    • Terms of Use
    • Privacy Policy
    • Disclaimer

    About Scholar99.com

    I am Ravi, the founder of Scholar99.com. Our primary intention of starting this blog is to write qualitative tutorials that are essential and useful in every IT professional’s career.

    Popular Posts

    • Work Performance Data Vs Information Vs Reports – The Key …
    • 7 Important Project Management Terms Every PMP Aspirant Must Know
    • 7 Powerful Steps To Create PMP Study Plan That BEST …
    Copyright © 2025 Scholar99.com
    Copyrights Text Powered by Scholar99.com | Terms of Use | Privacy Policy | Disclaimer

    Ad Blocker Detected

    Our website is made possible by displaying online advertisements to our visitors. Please consider supporting us by disabling your ad blocker.

    Refresh