Scholar99.com

Learning Simplified
Menu
  • Home
  • Project Management
  • About Us
  • Contact Us
  • Privacy Policy
  • Disclaimer

Home » Project Management » Program Evolution And Review Technique (PERT) & Three Point Estimates

Program Evolution And Review Technique (PERT) & Three Point Estimates

Ravi September 3, 2017
Share
Share
Tweet
Pin
0 Shares

Program Evolution and review technique (PERT) is a estimation technique which is used to find out the project duration or the project cost.

Before going to the details of program evolution and review technique (PERT), let us understand what is this estimation thing all about.

When the project manager identifies the project tasks he or she first needs to decompose the tasks into the smaller activities. Then the project manager needs to find out how much time requires for each of the activity to come up with the project estimate.

But the question is how does the project manager knows how much time it takes for each activity in the project?

Table of Contents

    • Single point estimation
    • Three point estimate
      • Three point Estimate Example:
      • Optimistic Estimate
      • Most Likely estimate
      • Pessimistic Estimate
    • Types of three point estimates
      • Simple Average estimate or triangular distribution
      • Program Evolution and Review Technique (PERT) or BETA distribution
    • Three Point Estimate Example
  • PERT and CPM (Critical Path  Method)
    • Conclusion

Single point estimation

The project manager needs to work with project team to find out if there is any historical data on the basis of which we can estimate the duration for each activity. This would definitely provide a basis for the estimate.

For example if an similar (or same) activity in a historical project took 2 weeks of time to complete the activity, this estimate can be used in the current project activity as well to calculate the project duration.

This is called single point estimation. However in all cases, we may not be able to find the activity duration from historical projects.

For example the project team has never done this kind of activity earlier. Or the project team is not sure at all how much time “exactly” the activity takes.

In such cases, the three point estimate will give better results.

Three point estimate

Program Evolution and review technique - PERT - Three point estimate

Three point estimate is of help in cases where the project team does not have any historical basis for the activity estimates.

In these cases the project manager sit with project team to understand three different estimates for each activity. They are

  • Optimistic (O) estimate
  • Most Likely (M) estimate
  • Pessimistic (P) estimate

Let us look at each of them with the below example.

Three point Estimate Example:

For example if the project says that this particular activity is going to take usually (normally) 10 days of time considering the nature of the activity. In the best case the activity is going to take 6 days for completion, if everything goes smoothly. In the worst case it would take 15 days to complete the activity.

Optimistic Estimate

When the project team is not fully aware of how much time exactly the activity takes, then they try to see what is the range that they can be suggest to the project manager.

Optimistic estimate is always a best case estimate in that range.

In the above example 6 days is the optimistic estimate.

Most Likely estimate

This is the most likely estimate for a specific activity. Meaning that the project team thinks that in most probable cases, this activity should complete within this estimate.

In the above example 10 days is the most likely estimate.

Pessimistic Estimate

This the worst case estimate. Meaning that considering any unforeseen problems, even in worst case the project team can complete this specific activity within this pessimistic estimated duration.

In the above example the pessimistic estimate is 15 days.

Types of three point estimates

Now with the help of all these three estimates optimistic (O), most likely (M) and pessimistic (P), we can calculate the three point estimate, which is proved to be more accurate than the single point estimate.

There are 2 popular ways of calculating the three point estimates. They are

  • Simple Average estimate or triangular distribution
  • Program Evolution and Review Technique (PERT) or beta distribution

Simple Average estimate or triangular distribution

When you plot this three estimates on a graph, then it looks like a tringle and hence the name triangular distribution.

Simple average estimate or triangle distribution is calculate by taking a simple average of the three values optimistic, most likely and pessimistic estimates.

Triangular distribution Estimation = (Optimistic  Estimate + Most Likely Estimate + Pessimistic Estimate)/3

This will definitely provide a better result than the single point estimate. However the only problem is that triangular distribution considers the same weightage for all the 3 estimates. Meaning that for optimistic, pessimistic and most likely estimates are taken by simple average, without any weightage.

Program Evolution and Review Technique (PERT) or BETA distribution

On the other hand program evolution and review technique (PERT) uses more weightage to the most likely estimate compared to the other two estimates pessimistic and optimistic.

This is because most like estimates has more probability than the other two. Hence this is even more accurate than the triangular distribution.

We can calculate PERT as follows:

PERT Estimation =  (Optimistic  Estimate +4 x( Most Likely Estimate )+ Pessimistic Estimate)/6

In the above formula most likely estimate has given more weightage (4) than the other two (pessimistic and optimistic).

Three Point Estimate Example

Let us take a simple example of how to calculate the 3 point estimates.

An activity pertaining to a construction project takes 5 weeks in best case,  7 weeks is the most likely case and 12 weeks is what it takes for the worst case.

So if we calculate three point estimates for this example

Triangular distribution estimate = (5+7+12)/3 =8 weeks

On the other hand the Program evolution and review technique or PERT estimate = (5+(4*7)+12)/6 = 45/6 = 7.5 weeks

PERT and CPM (Critical Path  Method)

PERT and CPM are two different type of methods. Program evolution and review technique (PERT) is used when there are uncertain or unknown activities in the project. On the other hand critical path method considers well defined project activities.

PERT is a probabilistic model whereas CPM is a deterministic model.

Generally PERT is more suitable for R&D type of projects, where the activities are done by the project team for the first time. On the other hand CPM (Critical path method) is used in non-R&D projects, where the activities are well established.

Finally PERT greatly helps to find out activity duration of a project, while CPM helps in understanding the critical path in the project.

Conclusion

To summarize, we have seen what is a single point estimate and is when is it relevant to use.

What are three point estimate is and different types of three point estimates.

Importantly we have seen how to calculate program evolution and review technique (PERT) and also the triangular distribution.

Finally we have ended the topic with a small comparison between PERT and CPM.

Share
Share
Tweet
Pin
0 Shares
Share
Tweet
Pinterest
Linkedin
Reddit
Email
Prev Article
Next Article

Related Articles

PMBOK 6th Edition changes in 2018
The much awaited period for PMBOK 6th edition is over. Indeed, …

PMBOK 6th Edition Changes In 2018

FLOAT-TOTAL FLOAT-FREE FLOAT
Float tells you about the flexibility you have as a …

How to calculate Float, Free Float, Total Float Using ES, EF, LS and LF

What Is A Project In Project Management?
Most of us are part of some or the other …

What Is A Project in Project Management?

Scope Creep in Project Management
One of the top drivers of project success is proper …

What Is Scope Creep in Project Management? 9 Causes of Scope Creep

Leave a Reply

Cancel reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.




Popular Posts

    Recent Posts

    • Construction-Assistant-Project-Manager-Salary-in-usa-and-india
      Construction Assistant Project Manager Salary in USA & India
    • What-is-a-Project-Scope-in-Project-Management
      What Is a Project Scope in Project Management?
    • What is Gold Plating
      What is Gold Plating in Project Management? Top 5 Causes …
    • What Is A Project In Project Management?
      What Is A Project in Project Management?
    • What-is-Pareto-Chart
      What is a Pareto Chart? | 80 20 Rule | …

    Find us on Facebook

    Get more stuff

    Subscribe to our mailing list and get interesting stuff and updates to your email inbox.

    Thank you for subscribing.

    Something went wrong.

    we respect your privacy and take protecting it seriously

    Scholar99.com

    Learning Simplified

    Important Links

    • About Us
    • Contact Us
    • Terms of Use
    • Privacy Policy
    • Disclaimer

    About Scholar99.com

    I am Ravi, the founder of Scholar99.com. Our primary intention of starting this blog is to write qualitative tutorials that are essential and useful in every IT professional’s career.

    Popular Posts

    • Work Performance Data Vs Information Vs Reports – The Key …
    • 7 Important Project Management Terms Every PMP Aspirant Must Know
    • 7 Powerful Steps To Create PMP Study Plan That BEST …
    Copyright © 2025 Scholar99.com
    Copyrights Text Powered by Scholar99.com | Terms of Use | Privacy Policy | Disclaimer

    Ad Blocker Detected

    Our website is made possible by displaying online advertisements to our visitors. Please consider supporting us by disabling your ad blocker.

    Refresh