Scholar99.com

Learning Simplified
Menu
  • Home
  • Project Management
  • About Us
  • Contact Us
  • Privacy Policy
  • Disclaimer

Home » Project Management » Types Of Dependencies In Project Management

Types Of Dependencies In Project Management

Ravi September 8, 2017
Share10
Share6
Tweet
Pin
16 Shares

Dependencies in project management shows the relationship between project activities. When you plan to schedule activities, you as a project manager would figure out the relationship between these activities in order to figure out the order of the execution of the activities.

In the activity on node (AON) or precedence diagramming method (PDM), we have seen how the dependencies are shown between the activities.

Also we have seen Activity on arrow diagramming method is limited to show only finish to start (FS) dependencies.

If you observe, the words predecessor and successor are relative words. Meaning that when you use one of these words, you need to mention about at least two activities. For example activity A is a predecessor to activity B.

Dependencies in Project Management

Table of Contents

  • Types of Dependencies in Project Management
    • Finish To Start (FS)
    • Finish-to-finish (FF)
    • Start-to-start (SS)
    • Start-to-finish (SF)
  • Nature of Dependencies in Project Management
    • External dependencies
    • Discretionary dependencies
    • Mandatory dependencies
    • Internal dependencies
  • Lead and Lag
  • Conclusion

Types of Dependencies in Project Management

There are four types of dependencies in project management. They are

  1. Finish-to-start (FS)
  2. Finish-to-finish (FF)
  3. Start-to-start (SS)
  4. Start-to-finish (SF)

Now let us look at some of the interesting things, how to we pronounce or understand this concepts or terminology.

In all the above dependencies in project management, there are two letter that we denoted in the short form. For example FS, FF, SS, SF.

In this the first letter always tells about the predecessor activity. And the second letter always tells about the successor activity. Meaning that in FS (Finish-to-start) dependency, we can read and understand this as the Successor activity cannot start until the predecessor finish the activity.

When we are talking about the predecessor activity and successor activity,

  • Always the predecessor activity is independent. Meaning that there is no constraint on the predecessor.
  • The constraint of dependency is always on the successor activity.

For all the four dependencies in project management, we can read the statement with the below template statement.

Successor activity cannot “finish/start” until the predecessor activity “finish/start”.

Let us start using the above template for all four dependencies in project management.

Finish-to-start (FS) – Successor activity cannot start until the predecessor activity finish.

Finish-to-finish (FF) – Successor activity cannot finish until the predecessor activity finish.

Start-to-start (SS) – Successor activity cannot start until the predecessor activity start.

Start-to-finish (SF) – Successor activity cannot finish until the predecessor activity start.

Now let us look at each of these dependencies in project management in detail one after the other.

Finish To Start (FS)

Finish to start dependency

Finish-to-start (FS) is the most simplest one among the dependencies in project management. This is the most frequently used dependency when sorting the order of activities in the project.

PMBOK guide defines the finish to start dependency as a logical relationship in which a successor activity cannot start until a predecessor activity finished.

For example in the waterfall SDLC model, the development activity (successor) cannot start until the design finish (predecessor activity).

Finish-to-finish (FF)

Finish to finish dependency

PMBOK guide defines the finish to finish dependency as a logical relationship in which a successor cannot finish until the predecessor activity has finished.

Meaning that even the successor activity B finishes early it has to wait for activity A to finish first and then only the activity B can finish.

For example, the broadcasting activity cannot finish until the tournament finishes. In this case tournament is the predecessor activity and the broadcasting is the successor activity.

Start-to-start (SS)

Start to Start dependency

PMBOK guide defines the start to start dependency as a logical relationship in which a successor cannot start until the predecessor activity has started.

So the successor activity B cannot start independently on its own. It has to wait for activity A to start first and then only the activity B can start.

For example, Sales team is going to sell the product after at least documenting the necessary sales information on the product. In this scenario, start to start dependency is stated as follows.

The sales team can’t start selling the product until the basic product road map documentation starts.

Start-to-finish (SF)

Start to finish dependency

This is the rarest one among the other dependencies in project management.  And hence it is very difficult to visualize this with an example.

PMBOK guide defines the start to finish dependency as a logical relationship in which a successor cannot finish until the predecessor activity has started.

The successor activity B cannot finish until the start of the predecessor activity A.

PMBOK has an example for this as, the first security guard shift (successor) cannot finish until the second security guard shift (predecessor) starts.

Nature of Dependencies in Project Management

We have seen four types of dependencies in project management. Now depending on nature of the dependency it can be classified into the following.

  • External dependencies
  • Discretionary dependencies
  • Mandatory dependencies
  • Internal dependencies

External dependencies

In the project, sometime we may have depend on the activity beyond our work. These are generally known as prerequisites for the project, but still they are dependencies for activities in the project.

For example, you see that generally to perform any installation, you may be dependent on the hardware and software procurement, which may be procured from an external party.

Discretionary dependencies

These dependencies are not really the barriers. Instead these dependencies are a matter of preference. Meaning that they are good to fulfill as a matter of preference.

Mandatory dependencies

As the name says these dependencies are mandatory and must fulfill at any cost. For example until you download the software, you can install the software on the server.

Internal dependencies

These dependencies usually are within the project team’s control and hence the name internal dependencies.

Lead and Lag

Let us start with lag, as we all know that lag just means delay.

As per the PMBOK guide,

  • A lag is the amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity. Sometimes after completing the predecessor activity, you may have to wait for the successor activity to start in a finish to start dependency. This is nothing but a lag.

Lag

 

  • On the other hand a lead is the amount of time whereby a successor activity can be advanced with respect to a predecessor activity. This could be because you wanted to apply some of the schedule compression techniques for example.

Lead

Conclusion

To summarize we have started with the dependencies in project management. Then we have seen 4 types of dependencies in project management. They are finish to start, start to start, finish to finish, start to finish.

Also we have seen that depending on the nature of dependencies they categorize in to external, internal, discretionary and mandatory dependencies.

Finally we have conclude the post by looking at what a lead is and what a lag is?

These concepts are extremely important from the PMP exam perspective and also in general in planning and scheduling the project activities as part of project management.

Share10
Share6
Tweet
Pin
16 Shares
Share
Tweet
Pinterest
Linkedin
Reddit
Email
Prev Article
Next Article

Related Articles

What-is-a-project-Scope-Statement-in-project-management
Project Scope Statement includes all the project work that you …

What Is a Scope Statement In Project Management?

Organizational Structures
Organizational structures explains your organization culture in terms of classifying …

Types Of Organizational Structures – Must Read Concept for PMP

Types of Procurement Contracts
Types of procurement contracts describes the types of contracts during …

Types Of Procurement Contracts In Project Management

Fast Tracking and Crashing - Schedule Compression Techniques in Project Management
Fast tracking and crashing are the schedule compression techniques in …

Fast Tracking And Crashing – Schedule Compression Techniques

No Responses

  1. Anonymous

    Visitor Rating: 5 Stars

    August 22, 2018

Leave a Reply

Cancel reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.




Popular Posts

    Recent Posts

    • Construction-Assistant-Project-Manager-Salary-in-usa-and-india
      Construction Assistant Project Manager Salary in USA & India
    • What-is-a-Project-Scope-in-Project-Management
      What Is a Project Scope in Project Management?
    • What is Gold Plating
      What is Gold Plating in Project Management? Top 5 Causes …
    • What Is A Project In Project Management?
      What Is A Project in Project Management?
    • What-is-Pareto-Chart
      What is a Pareto Chart? | 80 20 Rule | …

    Find us on Facebook

    Get more stuff

    Subscribe to our mailing list and get interesting stuff and updates to your email inbox.

    Thank you for subscribing.

    Something went wrong.

    we respect your privacy and take protecting it seriously

    Scholar99.com

    Learning Simplified

    Important Links

    • About Us
    • Contact Us
    • Terms of Use
    • Privacy Policy
    • Disclaimer

    About Scholar99.com

    I am Ravi, the founder of Scholar99.com. Our primary intention of starting this blog is to write qualitative tutorials that are essential and useful in every IT professional’s career.

    Popular Posts

    • Work Performance Data Vs Information Vs Reports – The Key …
    • 7 Important Project Management Terms Every PMP Aspirant Must Know
    • 7 Powerful Steps To Create PMP Study Plan That BEST …
    Copyright © 2025 Scholar99.com
    Copyrights Text Powered by Scholar99.com | Terms of Use | Privacy Policy | Disclaimer

    Ad Blocker Detected

    Our website is made possible by displaying online advertisements to our visitors. Please consider supporting us by disabling your ad blocker.

    Refresh