Scholar99.com

Learning Simplified
Menu
  • Home
  • Project Management
  • About Us
  • Contact Us
  • Privacy Policy
  • Disclaimer

Home » Project Management » Critical Path Method (CPM) – The Ultimate Guide To Critical Path Method

Critical Path Method (CPM) – The Ultimate Guide To Critical Path Method

Ravi September 16, 2017
Share
Share
Tweet
Pin
0 Shares

Critical path method (CPM) is the most important concept to understand for the PMP Exam. Once the project manager defines the project activities, activity duration and figure out the sequence of activities in the project, it is time for the project manager to see and analyze the critical path in the project.

This is done by creating a network diagram using all the activities, activity duration and dependency between the activities. And finally figuring out the longest path in the project, which is called critical path in project management terms.

Table of Contents

    • Critical Path Method (CPM)
    • Critical Path Definition – What is Critical Path In Project Management
      • Importance Of Critical Path For The Project Manager
    • How To Find Out The Critical Path Using Critical Path Method (CPM) – Steps
      • Step 1 – create a network diagram
      • Step 2 – Figure out all the paths in the project network diagram
      • Step 3 – Calculate the length of each path.
      • Step 4 – Find out the critical path, which is the longest path in the project.
    • Critical Path Method Example With Solution
      • Step 1 – create a network diagram
      • Step 2 – Figure out all the paths in the project network diagram
      • Step 3 – Calculate the length of each path.
      • Step 4 – Find out the critical path, which is the longest path in the project.
  • Conclusion

Critical Path Method (CPM)

Critical path method (CPM) is the method, which project manager uses to figure out the critical path in the project.

Critical Path Definition – What is Critical Path In Project Management

The Critical path is defined as the longest path in the project. or

Critical path can also be defined as the shortest duration in which the project can complete.

What does it mean?

Critical path means that, the project manager do not have any luxury of delaying the project, when performing the activities on critical path. So every activity on the critical path must complete on time for the project to complete on time. A delay in any of the activities on critical path, will delay the whole project.

So critical path can also define as the collection (path) of activities that will delay the whole project, if any of them are delayed.

Well. But why should I know about it as a project manager?

Importance Of Critical Path For The Project Manager

As project manager your main objective is to look at the activities in the project, for any slippages and to correct them as needed. Especially with respect to critical path the project manager has to understand two points.

  1. Understand the critical path and make sure each activity on the critical path is completed on time. Knowing the critical path of the project will help the project manager to use any of schedule compression techniques to keep the critical path activities on track in terms of timelines.
  2. Understand the activities which are not on the critical path. This will give a room for the project manager to play with the activities, if there are any delays with any of them. Meaning that this gives project manager some amount of freedom to consider the delays in one or more activities without impact the overall timelines of the project.

I got it know. But still would it be so important for me to understand to a great detail about it.

Yes. You need to understand the critical path method (CPM) completely in order to implement this in your project while performing the schedule management. Also from PMP exam perspective this concept is at most important. So to understand this in more detail we will traverse through a simple example.

How To Find Out The Critical Path Using Critical Path Method (CPM) – Steps

Here are the simple steps to find out the critical path in the project.

Step 1 – create a network diagram

With the help of activities, activity durations, dependencies create the network diagram using either of the methods activity on arrow (AOA) or activity on node (AON).

To keep it simple, we have followed precedence diagraming method (PDM) or activity on node (AON) method to create the network diagram in this blog post.

Step 2 – Figure out all the paths in the project network diagram

List down each of the paths in the project. Each path in the project represents activities to be performed in parallel with other paths.

Remember here that lot of PMP aspirants get confused that the paths are alternative to one another to finish the project. But this is not true.

All project activities are scatter across these paths based on the dependencies between the activities. And hence every path and every activity in each path must complete for a successful closure of the project.

Step 3 – Calculate the length of each path.

As we have charted out different paths exists in the project. It is time to calculate the duration of activities in each path, which we call it as the total length of the activities in that particular path.

Step 4 – Find out the critical path, which is the longest path in the project.

Eventually the longest path is called as critical path in the project. Meaning that any delay in the activities that are existing on critical path will delay the whole project.

Now since we have seen the steps to calculate critical path using critical path method (CPM), let us look at a simple example to understand it practically.

Critical Path Method Example With Solution

Critical Path Method

Let us take a simple example of baking a pizza at home to introduce some fun while learning this concept.

Activity IDActivitiesDuration
(in Minutes)
PredecessorNotes
AList down the ingredients required5StartAll required ingredients for baking the pizza
BPurchase the spices, mozzarella cheese and veggies30Apurchase from nearby store
CMix the dough and keep it ready20AA is predecessor as you need ingredients such as yeast to mix with dough
DBake the pizza30B,CBake the pizza in the oven
EDecorate (present) and Serve it15 DPresent it to make the looks wonderful

Step 1 – create a network diagram

Let us create the network diagram with the above activity information.

Step 2 – Figure out all the paths in the project network diagram

Now from the above diagram let us figure out the paths as follows.

Path 1:  START=>A=>B=>D=>E=>Finish

Path 2:  START=>A=>C=>D=>E=>Finish

Step 3 – Calculate the length of each path.

Now calculate the length of each path by adding the activity durations in that path.

Path 1 Length = 5+30+30+15 =80 mins

Path 2 Length = 5+20+30+15 = 70 mins

Step 4 – Find out the critical path, which is the longest path in the project.

It means that the total duration of activities in path 1 is 80 mins.

And the total duration of activities in path 2 is 70 mins.

So as we learned the critical path is the longest path (duration) in the project. In other words critical path is the shortest duration within which the project can complete.

So path 1 is longest duration path in the project. Hence the activities in path1 are considered to be on critical path and requires to be complete on time in order for the project to complete on time.

Conclusion

So Critical path method (CPM) is an important concept to understand both for the PMP exam and also for the project management in your projects.

Also we have seen what a critical path method is and also learn that project manager has to focus more on activities that are on critical path to avoid any delays in the project.

Finally we have seen the steps to calculate the critical path in the project and we calculate the critical path with the help of an example.

Share
Share
Tweet
Pin
0 Shares
Share
Tweet
Pinterest
Linkedin
Reddit
Email
Prev Article
Next Article

Related Articles

Project scheduling tools and techniques
Project scheduling tools and techniques used in develop schedule process …

Project Scheduling Tools And Techniques – Develop Project Schedule

Motivation Theories
Motivation theories are part of Human resource management knowledge area …

5 Popular Motivation theories – Every Project Manager must know

Stages of team development
Eventually stages of team development will describe the process of …

5 Stages of Team Development – What PM Should Do In Each Stage?

Interpersonal skills of project manager
Interpersonal skills are the soft skills that a project manager …

Interpersonal Skills Of The Project Manager

Leave a Reply

Cancel reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.




Popular Posts

    Recent Posts

    • Construction-Assistant-Project-Manager-Salary-in-usa-and-india
      Construction Assistant Project Manager Salary in USA & India
    • What-is-a-Project-Scope-in-Project-Management
      What Is a Project Scope in Project Management?
    • What is Gold Plating
      What is Gold Plating in Project Management? Top 5 Causes …
    • What Is A Project In Project Management?
      What Is A Project in Project Management?
    • What-is-Pareto-Chart
      What is a Pareto Chart? | 80 20 Rule | …

    Find us on Facebook

    Get more stuff

    Subscribe to our mailing list and get interesting stuff and updates to your email inbox.

    Thank you for subscribing.

    Something went wrong.

    we respect your privacy and take protecting it seriously

    Scholar99.com

    Learning Simplified

    Important Links

    • About Us
    • Contact Us
    • Terms of Use
    • Privacy Policy
    • Disclaimer

    About Scholar99.com

    I am Ravi, the founder of Scholar99.com. Our primary intention of starting this blog is to write qualitative tutorials that are essential and useful in every IT professional’s career.

    Popular Posts

    • Work Performance Data Vs Information Vs Reports – The Key …
    • 7 Important Project Management Terms Every PMP Aspirant Must Know
    • 7 Powerful Steps To Create PMP Study Plan That BEST …
    Copyright © 2025 Scholar99.com
    Copyrights Text Powered by Scholar99.com | Terms of Use | Privacy Policy | Disclaimer

    Ad Blocker Detected

    Our website is made possible by displaying online advertisements to our visitors. Please consider supporting us by disabling your ad blocker.

    Refresh